The Transmission Company of Nigeria has raised the alarm over submerged transmission lines in Lagos following torrential rains, declaring force majeure on its Oworonshoki 132/33kV and Lekki 330/132kV substations.
The company cited difficulty in evacuating power due to flooding, which has affected key facilities.
This development could worsen the already unstable power supply in Nigeria’s commercial capital, leaving businesses and residents in the dark.
TCN assured the public that efforts are underway to pump out water and restore normal operations, but did not give a timeline.
Environmental experts have blamed poor drainage and lack of maintenance for recurrent flooding.
The situation underscores the vulnerability of critical infrastructure to climate change, with many calling for urgent investment in resilient systems.